How should you control an ISCC PLUS intake change? Map ERP codes to official material entries, approve exceptions and test the audit trail with a worked PDCA exercise.

Before changing an ISCC PLUS intake configuration, map each ERP item to its official material entry, raw-material or intermediate status, relevant site and certification scope. Approve the mapping before release. Two internal item codes can represent one material entry; an additional intermediate can change the surveillance assessment. Counting stock codes is not a reliable substitute for understanding the inputs.
This guide uses ISO-style change control and Plan, Do, Check, Act to implement the ISCC System Update of 25 November 2026. These are ISCC PLUS changes, not new ISO requirements. The exercise and suggested records are original, illustrative Get-ISO practice, not official exam questions, a mandatory operator examination or a qualification.
What changed, who is affected and when?
The update concerns PLUS 204 section 3.2.2 and PLUS 201 sections 3.2.1 and 3.2.5. It applies from 25 November 2026 to standalone-document audits; previous-version audits within the transition retain that basis. From 1 January 2027, all PLUS audits use the updated requirements and applicable standalone documents. Audit date determines applicability.
For processing units, post-initial-certification surveillance is mandatory for raw-material-plus-intermediate intake, or at least two distinct raw material entries including a high-risk entry. Differences in sustainability characteristics of one entry do not create multiple inputs; their quantities and characteristics must remain identifiable. Only intermediates, only non-high-risk raw materials, or one high-risk raw entry alone do not trigger this processing rule.
Audit risk is a separate decision. High-risk listed materials mandate factor 2.0 at collecting points, central offices of points of origin and individually certified points of origin. Other scopes require certification-body assessment; other mandatory criteria still apply. A mandatory high-risk scope makes a multi-scope audit high overall, with minimum verification of every activity. Existing surveillance timing, on-site, no-early-recertification-substitution and gap rules remain; no certified transactions does not remove the obligation.
These PLUS rules should not be applied automatically to EU or CORSIA. Our ISCC PLUS surveillance and risk guide explains the wider distinction.
Supervisor exercise: two stock codes and one proposed new input
A fictional processing unit is preparing for an initial standalone-document audit on 2 December 2026. Its controlled mapping identifies one high-risk raw material entry. Purchasing uses two ERP codes for that same entry because the supplies carry different sustainability characteristics. A buyer now proposes a purchased intermediate for the same certified process. The supplier’s quotation calls it “processed material”, but the classification evidence has not been reviewed.
Your task: Would you count the two stock codes as two raw material entries? Would you release the proposed input? Identify the owner, approval and records needed to answer both questions.
The identifiers below are fictional teaching labels, not ISCC material-list names. In a real system, insert the exact applicable official entry and retain the evidence supporting its classification and risk status.
| ERP code | Controlled mapping | Operational decision |
|---|---|---|
| RM-101 | RAW-A; high-risk raw entry; characteristic set A | Retain its own lot, characteristics and quantity records |
| RM-102 | Same RAW-A entry; characteristic set B | Do not count it as a second entry solely because its code differs |
| NEW-201 | Proposed INT-B; intermediate classification unconfirmed | Keep unreleased pending technical review and the relevant certification-body assessment |
Plan: define the change before changing the master data
The certification coordinator owns the applicability review. Purchasing gathers supplier evidence; the technical manager assesses the material and processing description; the ERP administrator implements the approved mapping. Receiving supervisors use the released instruction. The appointed certification body determines audit risk and confirms applicable scheme treatment within its role.
Create one change record with the site, scope, proposed effective date, audit date and document basis. Attach the applicable material-list version, supplier description, upstream documentation and the proposed flow into the process. Record each official entry, raw/intermediate status and high-risk flag separately from the commercial stock code. Include who checked the evidence and what remains unresolved.
In this example, two codes still map to RAW-A. That fact alone does not trigger the processing surveillance rule. If NEW-201 is confirmed as an intermediate and added to the intake, the raw-plus-intermediate configuration does meet that rule. The coordinator records that conclusion and obtains the certification body’s corresponding audit and surveillance arrangements. Neither conclusion automatically establishes the audit risk factor.
Do: release an approved configuration and control exceptions
The supervisor keeps NEW-201 unreleased while evidence is incomplete. Purchasing arranges to defer delivery or use a specifically approved holding arrangement; it does not relabel the input to fit an existing code. A supplier’s word “processed” cannot establish the scheme classification on its own.
Once reviewed, the ERP administrator releases a versioned mapping with an effective date and restricted editing rights. Receiving staff check the item, supplier, lot, documents and intended location against that mapping. Preserve the old version so earlier receipts remain traceable to the criteria then used.
An urgent-order exception needs a named approver, reason, permitted holding or routing action, expiry and closure evidence. It cannot waive ISCC requirements or authorise unsupported certified claims. If a discrepancy is found after receipt, identify the affected stock and records and escalate before further certified use or dispatch.
For an already certified site changing its configuration, record when the change actually occurs and refer it to the certification body to establish the applicable action. Do not invent a new surveillance deadline or assume that a future recertification replaces an existing obligation.
Check: reconcile the mapping with what actually happened
The internal reviewer tests both accepted and rejected paths in a sandbox or clearly marked training record. RM-101 and RM-102 should retain separate characteristics and quantities while resolving to the same official entry. An unapproved NEW-201 receipt should remain blocked from the certified workflow. Keep the test inputs, observed result, reviewer and corrective action; do not issue simulated sustainability declarations as real documents.
An auditor can sample the released map and reconcile it to purchase orders, supplier evidence, receiving or weighbridge records, sustainability documentation, quantity bookkeeping and production use. Trace one receipt forward into the ledger and one ledger entry backwards to its source. Reconcile quantities by characteristic as well as total: a correct overall total can conceal an incorrect characteristic allocation.
Sample a master-data amendment and an exception too. Compare approval and effective dates with the first affected receipt, then check the certification body’s separate risk decision and surveillance plan or booking where required. A signed spreadsheet without matching operational records does not show that the control worked.
Act: remove the route around the control
If an ordinary user can create an unmapped item or overwrite a risk flag, the ERP owner corrects access and workflow rules. If the technical classification was wrong, the coordinator reviews affected receipts, claims and audit arrangements with the relevant owners and certification body. Retest the failed path and check the next affected receipt before closing the action.
The effectiveness measure is whether the approved configuration governs actual receipts and preserves traceable characteristics and quantities. Training attendance or a new procedure alone is insufficient. Keep the review tied to this intake change; the November bulletin does not introduce a new ISO qualification or generic environmental or safety procedure.
Discuss your ISCC PLUS intake and audit scope
Mason Ali is BM Certification’s ISCC representative for Australia and New Zealand. Get-ISO handles enquiries and coordinates the certification pathway. BM Certification makes certification decisions and issues certificates where it is the appointed certification body; its current ISCC directory listing includes ISCC PLUS.
Use the ISCC certification enquiry service or contact Get-ISO about initial certification, recertification or changing certification bodies. Include sites, activities, feedstocks and official material entries, intended product and market, current scheme/body, certificate expiry, proposed intake change and target audit date. For criteria-version changes, see our audit transition-date control exercise.
Sources and status checked on 27 November 2026
- ISCC’s original 25 November 2026 bulletin, section 2.3, checked against the public System Updates register, “Updated requirements for audit risk classification and mandatory surveillance audits”.
- ISCC document library, for the applicable PLUS 201, PLUS 204 and material-list versions. The bulletin supplements the documents pending their next relevant revisions.
- ASQ’s Plan, Do, Check, Act explanation, for the improvement method. The ERP workflow and exercise are independently developed implementation examples, not prescribed ISCC templates.
ISO’s catalogue identifies ISO 9001:2026 and ISO 14001:2026 as published, and ISO 45001:2018 as current with Amendment 1:2024. Those edition facts do not make the ISCC changes ISO requirements. This article addresses the specified PLUS update through management-system controls.
General guidance. Use the applicable standard, scheme documents and agreed engagement criteria. Examples are illustrative and do not establish a certification outcome.